Front
        Lobby Photo
 

College of Education

College of Education at the University of Illinois at Urbana-Champaign

Education Building Network Upgrade, 2007

Rooms affected:
Most of the project will be limited to the basement.  Since the wireless network and our classrooms are also receiving upgrades, many spaces on floors 1-3 will be affected.  For details, please view the list below.
Original Timeline:
(Work was scheduled for July 16 through December, 2007.)
Current Timeline:
  • [done] October-November: Remodeled new Data Center (room 63), including installation of chilled water cooling units, electrical infrastructure, conduits.
  • [done] Thanksgiving break: Replace network equipment in South CER (Hub C)
  • [in progress] December 18-21: Repull Hub A jacks (HA) in South half of building to South CER, Hub C (HC)
  • December 29-January 1: Move servers from North CER to new Data Center (room 63)
  • January 3-?: Remodel North CER for CITES exclusive use.
  • ?: Replace network equipment in North CER (Hub B)
  • Spring Break : Repull Hub A (HA) jacks in North half of building to North CER, Hub B (HB)
What to expect:
Expect noise during periods of construction, especially in the morning.
For offices affected, expect 3-4 scheduled visits from various tradespersons to complete the work.
Questions?
If you have any questions about the project, please contact Ryan Thomas or Tim Vruwink through the Help Desk at 244-6053.  Questions regarding facilities scheduling should be directed to Tammy Collins at 244-5714.

Rooms Affected:

All rooms in the basement are affected except the following:

32
32B
32C
32D
32E
32F
38A
38B
38G
38H
38K
38M
38Q
38R
38S

Only the following rooms in floors 1-3 will be affected:
101
110
120
128
140A
140B
150
162
166
170
176
188S
188B
192
210A
210E
242
260A
260
270E
270
288A
323
327/333
339
353
350
372
376
382
382
385
390