Education Building Network Upgrade, 2007
- Rooms affected:
- Most of the project will be limited to the basement. Since the wireless network and our classrooms are also receiving upgrades, many spaces on floors 1-3 will be affected. For details, please view the list below.
- Original Timeline:
- (Work was scheduled for July 16 through December, 2007.)
- Current Timeline:
- [done] October-November: Remodeled new Data Center (room 63), including installation of chilled water cooling units, electrical infrastructure, conduits.
- [done] Thanksgiving break: Replace network equipment in South CER (Hub C)
- [in progress] December 18-21: Repull Hub A jacks (HA) in South half of building to South CER, Hub C (HC)
- December 29-January 1: Move servers from North CER to new Data Center (room 63)
- January 3-?: Remodel North CER for CITES exclusive use.
- ?: Replace network equipment in North CER (Hub B)
- Spring Break : Repull Hub A (HA) jacks in North half of building to North CER, Hub B (HB)
- What to expect:
- Expect noise during periods of construction, especially in the morning.
For offices affected, expect 3-4 scheduled visits from various tradespersons to complete the work.
- Questions?
- If you have any questions about the project, please contact Ryan Thomas or Tim Vruwink through the Help Desk at 244-6053. Questions regarding facilities scheduling should be directed to Tammy Collins at 244-5714.
Rooms Affected:
All rooms in the basement are affected except the following:
32
32B
32C
32D
32E
32F
38A
38B
38G
38H
38K
38M
38Q
38R
38S
Only the following rooms in floors 1-3 will be affected:
101
110
120
128
140A
140B
150
162
166
170
176
188S
188B
192
210A
210E
242
260A
260
270E
270
288A
323
327/333
339
353
350
372
376
382
382
385
390